GPM Gold Project

Armenia

Glencore Technology Help GPM To Quadruple Plant Recovery

GeoProMining LLC, or GPM, have been using Albion Process™ to successfully increase recovery from sulphide concentrates in their Ararat plant from 20% to over 98%.

This exceeded expectations and targets. The plant was commissioned in June 2014 and achieved full capacity after just three months. 

GPM own and operate the Zod Gold Mine and Ararat Processing Plant in Armenia to produce gold and silver bullion.

In order to expand, GPM needed to treat the underlying sulphide material at the Zod mine which achieved around 20 to 30% gold recovery through their existing conventional CIL flowsheet.

In 2010, GPM approved a refurbishment project at the Zod Mine and Ararat Processing Plant – in increased crushing capacity to deal with the harder ore and a refurbishment and re-commissioning of the existing flotation plant.

They added to this the installation of a new Albion Process™ plant for the oxidation of the sulphide concentrate prior to its treatment in the existing Carbon in Leach plant. The new flowsheet would be configured such that the CIL would treat flotation tailings and oxidised residue from the Albion Process™.

The lump sum design and supply package from Glencore Technology included an M3000 IsaMill™ grinding package, twelve ZipaTanks™ modular leach and slurry storage reactors, a 10 m diameter high rate thickener, 120 tpd oxygen plant and 140 tpd limestone grinding plant. Also included were 54 HyperSparge™ oxygen injection spargers, designed to achieve supersonic injection of oxygen gas for improved reaction kinetics.

  • M3000 IsaMill™ used to finely grind the feed to the Albion Process™
  • Agitators and Vent stacks on top of Albion Leach Reactors

The design basis for the Albion Process™ at GPM was oxidation of 100,000 tpa of concentrate to give an overall production of 100,000 TOz of gold per annum from concentrate and flotation tailings. The design recovery of gold from the Albion residue was 92% but the plant frequently achieves over 95% recovery with an overall plant-wide design recovery of 86% but commonly achieving 88%. 

The refurbishment project was commissioned in June 2014, with ramp-up occurring for the remainder of 2014.

The plant has achieved and exceeded nameplate production, treating in fact 120,000 tpa concentrate with an overall production of 120,000 TOz per annum.

Further, GPM successfully achieved an overall 88% plant-wide recovery exceeding the 86% design target due to better than design performance in the Albion Process™. 

The grade of concentrate has been more or less stable, and increased production might normally be expected to decrease as equipment is stretched.  But in GPM’s case, they’ve successfully kept the recovery above design using the Albion Process™.

GPM are currently evaluating an expansion project comprising a second line of an Albion Process™ Plant.

  • Albion Process™ leach train under construction - GPM Gold
  • HyperSparge™ units mounted on side of ZipaTank™ in the Albion Process leach train
  • GPM Gold limestone and oxygen plants provided by Glencore Technology